top of page
Project: P22-ROAD-03

Truck Staging and Calling Center

Project Stage: Construction

This construction project will develop a truck staging and calling lot serving the Granite City Harbor to reduce improper truck queuing along West 20th Street and Route 3. The project is funded by a grant from the Illinois Department of Transportation.


The project is expected to conclude at the end of CY2026.


Project Schedule:

  • September

    • Earthwork / Grading

  • October

    • Paving New Roadway Between 20th & Niedringhaus

    • Paving Intersection Tie-ins at Niedringhaus and 20th

    • Paving Truck Parking Lot

  • November

    • Complete Paving Detail Work

    • Backfill and Finish Grading

    • Electrical Work for Lighting Begins

  • December – Feb

    • Electrical Work for Lighting Completed

  • Feb – End (as weather allows)

    • Seeding

    • Striping of Pavement